Installation of new Condensate Separation Vessel
To remove existing Condensate separation vessel(CSV). We disconnected all pipework from the existing CSV, unbolted from the concrete pad and lifted it out with a Franna. Once this was completed, we then lifted the new CSV into place, bolted it to the ground and re-connected all pipework to allow the power station to be re-started.